The long-delayed rebuild of the Balykchy–Bokonbaevo–Karakol road — the main artery along Kyrgyzstan's Lake Issyk-Kul — should finally be finished in 2027, according to Transport Minister Talantbek Soltobaev.

The project, which began in 2021, has been a saga. Two large Kyrgyz firms won the first 141-kilometre stretch between Balykchy and Barskoon by promising to undercut foreign contractors, but they started building before proper design and cost documents existed, quoting prices that proved wildly optimistic. The war in Ukraine then pushed up fuel, metal and materials costs, the budget fell short and deadlines slipped — first to June 2025, then to August 2026.

Things have picked up. By the end of August, 135 of the 141 kilometres on the first section were done, with just six kilometres of asphalt left, now being laid by the transport ministry's own crews. On the second stretch, from kilometre 141 towards Karakol, a contractor brought in last autumn has already paved 32 kilometres, with the full surface due by the end of the 2027 construction season. The road is being widened to four lanes throughout.

For travellers, this is genuinely good news. The south shore of Issyk-Kul is the cultural heart of the lake region: Bokonbaevo is the base for eagle-hunting demonstrations and yurt camps, Barskoon has its waterfall and gorge, and Karakol is the jumping-off point for treks in the Terskey Alatau and winter skiing at Karakol resort. Once the four-lane road is complete, the drive from Balykchy to Karakol becomes faster, smoother and far less bone-shaking — a real change for anyone doing a circuit of the lake or heading on to the Karkara valley and the Kazakh border.